Abenójar’s $190 Million IPO Puts 2029 Mine Plan to Test
Abenójar raised $190 million in London, but its below-offer debut puts mine construction and processing in focus ahead of its 2029 production target.

Abenójar Tungsten raised €170 million ($190 million) in London’s largest mining IPO since 2018 to develop its El Moto tungsten project in Spain, targeting commercial production in the first quarter of 2029.
Abenójar Tungsten (LON: ABT) has raised €170 million ($190 million) to build a new European tungsten mine, putting construction and processing delivery at the center of its investment case. The Spanish developer is targeting first commercial production from El Moto in the first quarter of 2029.
The financing gives investors exposure to a potential alternative to Chinese tungsten supply, but Friday’s share performance offered a restrained reception. Shares reached 105 pence in early-afternoon trading, up almost 3% but still below the 110-pence offering price. That was an intraday observation, not a closing quote.
The flotation was London’s largest mining initial public offering since 2018, Mining.com reported. Its scale makes it a notable financing event for the sector; delivering a producing mine remains a separate task.
Mine construction and processing must advance together
Construction is underway at El Moto in central Spain after 14 years of investment and development. Abenójar describes the project as one of the world’s largest and highest-grade undeveloped tungsten deposits. That assessment concerns the resource opportunity, rather than an operating mine already supplying customers.
Construction is underway at El Moto in central Spain after 14 years of investment and development.
The company is also in the early stages of developing a plant to refine concentrate from the mine. The production target therefore depends on more than completing mine construction: the associated processing infrastructure must also be ready to turn the deposit into commercial output.
Chief Executive Gonzalo García San Miguel said investor capital would be used to build the mine. For shareholders, progress on those physical assets is the concrete test of whether the IPO proceeds translate into the business the company intends to operate.
The European Union has designated both the mine and its planned processing facility as strategic projects, according to García San Miguel. The paired designations underline that Europe’s supply ambitions involve processing capacity as well as extracting ore.
Strategic demand does not remove delivery risk
Tungsten is used in defense systems, aerospace components, industrial cutting tools and electronics. China dominates global production and processing, prompting Western governments to seek alternative supplies. El Moto could contribute to that diversification, but only once construction and processing development reach commercial operation.
García San Miguel said London was chosen because of its concentration of specialist mining investors able to support long-term development. The IPO was the city’s biggest mining flotation by funds raised since Kazatomprom’s £311 million ($417 million) depositary-receipt listing in 2018.
Abenójar’s £522 million market capitalization also puts potential FTSE 250 inclusion within reach, although membership depends on other eligibility requirements. Neither index eligibility nor strategic-project status resolves the immediate operating challenge: completing the mine and processing infrastructure needed to meet the 2029 target.
Key facts
- IPO proceeds: €170 million ($190 million), London’s largest mining IPO since 2018.
- Share snapshot: LON: ABT — 105 pence in early-afternoon trading on October 30, 2026, below the 110-pence IPO price.
- Production target: First commercial production at El Moto targeted for the first quarter of 2029.
- Strategic designation: The mine and planned processing facility have EU strategic-project status, according to the CEO.