Merdeka’s Tujuh Bukit mine reported lower hauling costs and higher fleet productivity, offering a benchmark for Hexagon’s new deployment at Pani.

Merdeka subsidiary PT Bumi Suksesindo reduced load and haul costs by 14% at Tujuh Bukit after adopting Hexagon fleet technology and consulting, according to Hexagon.
A 14% reduction in load and haul costs at Merdeka’s Tujuh Bukit Gold Mine gives the company a concrete operating benchmark as Hexagon fleet technology expands to its Pani Operations. The results at the East Java mine followed the adoption of OP Pro fleet management software alongside Smart Centre consulting.
Hexagon reported that operator PT Bumi Suksesindo, a subsidiary of PT Merdeka Copper Gold Tbk, increased truck productivity by 11% and excavator productivity by 17% within six months. The figures, reported by International Mining, describe results at Tujuh Bukit—not a forecast for Pani.
Less waiting accompanied the productivity gains
The operational changes extended beyond equipment output. Truck queue time fell by 17%, while excavator hang time—the time loading equipment spends waiting for a truck—declined by 53%. Those reductions address the coordination between hauling and loading equipment, rather than simply the performance of individual machines.
OP Pro gives dispatch teams live information on fleet activity, production and equipment use. Its Optimiser assigns trucks dynamically according to loading equipment’s latest requirements, allowing dispatchers to adjust during a shift instead of waiting for retrospective reports.
For BSI, consistency across shifts was a central objective. Erik Wibisana Barnas, the company’s Technical Services Senior Manager, identified uneven fleet productivity between shifts as a challenge before implementation. That makes sustained use of the system an important part of interpreting the reported gains.
Erik Wibisana Barnas, the company’s Technical Services Senior Manager, identified uneven fleet productivity between shifts as a challenge before implementation.
Within six months, login compliance exceeded 99%, assignment compliance exceeded 95%, and Optimiser usage reached 90.8%. Hexagon’s consultants also provided training and adjusted the system to changing site conditions. The results therefore reflect a combined software-and-operating-practice rollout, not an isolated technology installation.
Fuel use and ore recovery add separate benefits
BSI also recorded a 9.5% reduction in fuel ratio and an annual emissions reduction of approximately 3,405 metric tons of carbon dioxide. These are distinct measures from the load and haul cost reduction; they should not be added together as separate financial savings.
High-precision GPS guidance delivered loading accuracy of less than 20 centimeters. Hexagon said that helped limit ore loss and dilution—unwanted material mixed with ore—and contributed to more than 600 ounces of additional gold recovery. This extends the reported benefit beyond moving material more efficiently to improving what the operation recovers.
Pani will test whether the operating gains travel
OP Pro has recently gone live at Pani under a five-year agreement. The initial deployment includes six high-precision and 40 low-precision systems, with another 47 low-precision truck units being processed.
Tujuh Bukit offers a useful reference because Merdeka already has experience combining dispatch software, operator adoption and consulting support. But Pani’s deployment is a new implementation, not evidence that the same productivity or cost reductions have been achieved there.
The practical comparison is whether Pani can establish similarly consistent system use and reduce equipment waiting time. Tujuh Bukit’s reported results provide specific measures against which that rollout can be assessed, while the site-specific tuning undertaken by Hexagon and BSI shows why replication requires more than installing the same software.
Key facts
- Load and haul costs: Down 14% at Tujuh Bukit following the technology and consulting rollout.
- Fleet productivity: Truck productivity rose 11% and excavator productivity rose 17% within six months.
- Additional gold recovery: More than 600 ounces, with high-precision GPS guidance contributing.
- Pani expansion: Five-year agreement; initial deployment includes six high-precision and 40 low-precision systems.