KEFI’s $87 Million Saudi Gold Plan Awaits Mining License

KEFI’s Saudi venture has conditionally approved Jibal Qutman, with a mining license and financing still central to its planned late-2026 development start.

Fiona Marchetti 3 min read
mountains, mines, nature, landscape, minerals, earth, darling, industry, colors

KEFI Gold and Copper’s Saudi joint venture conditionally approved the approximately $87 million first stage of Jibal Qutman, with development still dependent on a mining license and other procedural steps.

KEFI Gold and Copper’s Saudi joint venture has conditionally approved the approximately $87 million first stage of the Jibal Qutman gold project, putting the mining license and financing arrangements at the center of its planned fourth-quarter 2026 development start.

Gold and Minerals Company, known as GMCO, still needs to complete procedural requirements, including securing the mining license. The approval therefore advances the project without removing the conditions that stand between the development plan and work beginning.

Saudi industrial group ARTAR owns 87% of GMCO, while KEFI holds 13%. The venture has its own management, with oversight from both shareholders, according to Mining Technology.

KEFI’s contribution depends on the financing structure

GMCO expects equity contributions to cover around 50% of the required capital, with the balance potentially coming from other financing arrangements. That remains a proposed funding mix rather than a statement that all financing has been secured.

KEFI estimates its contribution to the initial phase at $10 million to $12 million over 24 months if supplied entirely as equity. That qualification matters: the figure describes an all-equity funding case for KEFI’s participation, not an unconditional payment due when development begins.

KEFI estimates its contribution to the initial phase at $10 million to $12 million over 24 months if supplied entirely as equity.

The financing structure and the license serve different purposes. The license is a regulatory requirement for advancing the mine, while the capital arrangements determine how the shareholders and any other funding providers would pay for it. Conditional approval alone settles neither issue.

The fourth-quarter target is also a development start, not a date for first gold production. Keeping those milestones separate is important when assessing how quickly Jibal Qutman could begin generating cash.

Gold-price assumptions drive a wide valuation range

The definitive feasibility study envisages an oxide-ore operation using carbon-in-leach processing, which dissolves gold from ore and captures it on activated carbon. Stage 1 is projected to recover approximately 258,000 ounces over seven years.

GMCO estimates post-tax net present value at $141 million to $275 million under gold-price assumptions of $3,000 to $5,000 an ounce. Its estimated internal rate of return ranges from 23% to 60%.

Net present value expresses projected future cash flows in today’s money; internal rate of return measures the project’s modeled investment return. These are scenario-based estimates, not realized earnings. The breadth of the ranges makes the assumed gold price an important part of the investment case alongside construction funding and permitting.

First-stage cash would support a broader Saudi portfolio

GMCO intends to use cash flow from Jibal Qutman’s initial phase to support further exploration and staged expansion across its projects. Its Saudi mineral resource totals around four million ounces of gold equivalent, with further developments planned at both Jibal Qutman and the Hawiah copper-gold project.

That gives the first stage a role beyond its own projected gold recovery: it is intended to help finance subsequent activity. Any delay in bringing it into operation would also push back that potential internal funding source, leaving the license and financing milestones relevant to the wider Saudi development plan.

Key facts

  • Initial investment: Approximately $87 million; conditional approval
  • KEFI funding estimate: $10 million–$12 million over 24 months if entirely equity-funded
  • Development target: Fourth quarter of 2026, subject to outstanding requirements
  • Projected gold recovery: Approximately 258,000 ounces over seven years